If you already live in east Brea, traffic is probably your first question about 1,100 new homes. If you’re thinking of buying in Brea 265, it’s your commute. The project’s Environmental Impact Report spells out both the projected trips and the street improvements the developer must make, so let’s go through them.
How many trips the EIR projected
The Draft EIR’s transportation analysis forecast that Brea 265 would generate about 9,351 daily trips on a typical weekday, including 634 in the morning peak hour (182 in, 452 out) and 893 in the evening peak hour (542 in, 351 out) [L1]. That’s the full 1,100-home buildout, not the first phase.
The analysis studied 22 intersections, including the SR-57 ramps at Lambert Road and Imperial Highway, Valencia Avenue at Lambert Road/Carbon Canyon Road, and several Imperial Highway intersections [L1]. Under current state rules, the main CEQA test is vehicle miles traveled rather than intersection delay, but the City still looks at intersection operations for planning [L1].
Lambert Road
Lambert Road is the main east-west route on the west side of the site. The EIR calls for widening it along the project frontage, from Valencia Avenue west to just east of Sunflower Street, to the City’s Major Arterial standard: three 12-foot travel lanes and an 8-foot bike lane in each direction, separated by a 14-foot median, in a 120-foot right-of-way [L1]. Today it has two lanes each way along that stretch [L1].
A 20-foot multipurpose trail is planned on each side outside the street [S2], and a lit pedestrian tunnel under Lambert Road would connect the neighborhoods north and south of it [S2].
Carbon Canyon Road (SR-142)
Carbon Canyon Road is a state highway (SR-142) and a regional commuter route; the City’s General Plan recognizes it “will continue to serve high volumes of regional traffic” [L1]. Brea 265 will not have an entry on Carbon Canyon Road [S2].
The EIR calls for widening the south side along the project frontage to the Major Arterial half-section, with three 12-foot eastbound lanes and an 8-foot bike lane [L1]. Today eastbound Carbon Canyon Road narrows from three lanes to two along the frontage [L1]. A multipurpose trail is planned on the south side [S2]. Because it is a state route, work there needs Caltrans concurrence [L1].
Valencia Avenue (SR-142)
Valencia Avenue splits the site into east and west halves. It’s already built to the City’s Primary Arterial standard with two travel lanes and a bike lane in each direction, and no additional travel lanes are proposed [L1] [S2]. The changes are mostly at the edges: new signalized entries, a landscaped parkway and a 20-foot multipurpose trail on the east side [S2].
The gated entry at Valencia Avenue and B Street must be set back at least 40 feet from the property line so cars waiting at the gate don’t back up onto Valencia [L1].
Rose Drive
On Rose Drive, the EIR calls for widening the east side along the frontage from Valencia Avenue south to Vesuvius Drive to the Primary Arterial standard, with two northbound lanes and a bike lane [L1]. To fit a second southbound lane, the design may need median or lane-width changes; as described, that lane would end as a right-turn lane at Vesuvius Drive [L1]. The gated entry at Rose Drive and P Street must be set back at least 60 feet [L1].
New signals and intersection fixes
The project is required to build signalized, full-access driveways on Lambert Road, Valencia Avenue and Rose Drive, plus a signal at Rose Drive and Vesuvius Drive [L1]. It must also prepare sight-distance studies for those driveways [L1].
Beyond its own entries, the developer pays the City’s transportation impact fees, a “fair share” toward future improvements [L1]. The EIR lists the improvements tied to Brea 265’s fair share for 2035 and 2045 conditions [L1]:
- Valencia Avenue at Lambert Road/Carbon Canyon Road: added left- and right-turn lanes and signal changes (needs Caltrans concurrence).
- Valencia Avenue at Birch Street/Rose Drive: a second southbound left-turn lane and signal changes (needs Caltrans concurrence).
- Rose Drive at Vesuvius Drive: restriping and a second southbound departure lane.
- Associated Road at Imperial Highway, and Rose Drive at Imperial Highway: restriping and signal changes (need Caltrans concurrence).
Aera’s former project website also described funding for 13 “smart” traffic signals citywide [S11]. I haven’t found that commitment in the EIR text I reviewed, so treat it as a project claim until the City confirms it.
During construction
Before construction work, the developer must get a City-approved traffic control plan covering any lane closures, hours when closures aren’t allowed, detours and flaggers [L1]. With grading under way on the east side [S1], expect periodic work on Rose Drive and Valencia Avenue frontage over the next few years.
What it means for your commute
For commute times from Brea 265 to job centers like Irvine, downtown Los Angeles and Ontario, see our commute guide. For freeway access points, see What’s Nearby.
This guide is general information, not legal, tax, insurance or lending advice. Builder policies, incentives, taxes and loan programs vary and change. Confirm anything that matters in writing with the builder, your lender, your insurance agent and a qualified tax or legal professional.
Sources for this page
- [L1] Brea 265 Specific Plan Draft EIR, Section 5.17 Transportation (PlaceWorks, Mar 2022), via CEQAnet (checked Nov 17, 2026)
Citations like [S24] point to the Brea 265 source list on our Sources page.